January 19 2011 Community Meeting Presentation (PDF)
Hoosier Plant Update

Week of February 6, 2012

Currently running under standard operating conditions

Week of January 30, 2012

Currently running under standard operating conditions

January 24-26, 2012 down for equipment maitenance. During this time the Scrubber and fan were inspected and PM'ed

Currently running under standard operating conditions

Week of January 23, 2012

Currently running under standard operating conditions

Week of January 16, 2012

Currently running under standard operating conditions

January 13, 2012 down for power outage in area

Week of Januare 9, 2012

Currently running under standard operating conditions

Week of Januare 2, 2012

Currently running under standard operating conditions

January 4, 2012 down for equipment maintenance. During this time the Scrubber and fan were inspected and PM'ed

_______________________________________________________________
Residential Public Meeting Notice

Meeting Date: Quarterly on the 3rd Wednesday of the month. 2012 schedule is below.

Meeting Time: 7:00 p.m.

Location: Dobisky Center
100 Riverside Avenue
Ogdensburg, NY 13669
Conference Room

Agenda: Review plant environmental performance

Presentation by Plant Manager
Question and Answer Session

Neighbor Requested Agenda Item: TBD

Please contact the Plant Manager prior to the meeting at 393-1813 x 111
To request an agenda item be added

All neighborhood residents are welcome.


“Hoosier Huddle” Public Meeting Schedule 2012:
March 21, 2012 7:00 p.m.
June 20, 2012 7:00 p.m.
September 19, 2012 7:00 p.m.
December 19, 2012 7:00 p.m.

A meeting schedule for 2013 will be provided at the December 2012 meeting.
____________________________________________________________________
Week of December 26, 2011

Currently running under standard operating conditions

December 24-26,2011 down for the holiday and equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of December 19, 2011

Currently running under standard operating conditions

December 15,2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of December 12, 2011

Currently running under standard operating conditions

Week of December 5, 2011

Currently running under standard operating conditions

Week of November 28, 2011

Currently running under standard operating conditions

November 30,2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of November 21, 2011

Currently running under standard operating conditions

Week of November 14, 2011

Currently running under standard operating conditions

Week of November 7, 2011

Currently running under standard operating conditions

November 3-6,2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of October 31, 2011

Currently running under standard operating conditions

Week of October 24, 2011

Currently running under standard operating conditions

Week of October 17, 2011

Currently running under standard operating conditions

Week of October 10, 2011

Currently running under standard operating conditions

Week of October 3, 2011

Currently running under standard operating conditions

October 4 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of September 26, 2011

Currently running under standard operating conditions

September 22 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of September 19, 2011

Currently running under standard operating conditions

Week of September 12, 2011

Currently running under standard operating conditions

September 8 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of August 22, 2011

Week of September 5, 2011

Currently running under standard operating conditions

Week of August 29, 2011

Currently running under standard operating conditions

September 2 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of August 22, 2011

Currently running under standard operating conditions

August 24 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of August 15, 2011

Currently running under standard operating conditions

August 16 and 18 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

August 12 and 13 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of August 8, 2011

Currently running under standard operating conditions

August 4 and 5 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of August 1, 2011

Currently running under standard operating conditions

Week of July 25, 2011

July 25 and 26 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of July 18, 2011

Currently running under standard operating conditions

Week of July 11, 2011

Currently running under standard operating conditions

__________________________________________________________________
Residential Public Meeting Notice Update

Meeting Date: Quarterly
2011 schedule is below.

Meeting Time: 7:00 p.m.

Location: Dobisky Center
100 Riverside Avenue
Ogdensburg, NY 13669
Conference Room

Agenda: Review plant environmental performance

Presentation by Plant Manager
Question and Answer Session

Neighbor Requested Agenda Item: TBD

Please contact the Plant Manager prior to the meeting at 393-1813 x 111
To request an agenda item be added

All neighborhood residents are welcome.
“Hoosier Huddle” Public Meeting Schedule for the rest of 2011:
September 21, 2011 7:00 p.m.
December 21, 2011 7:00 p.m.

A meeting schedule for 2012 will be provided at the December 2011 meeting.
____________________________________________________________________

July 11, 2011 down for equipment maintenance. During this time the Scrubber, and fan were inspected and PM'ed

July 10, 2011 down for equipment maintenance. During this time the cyclone was inspected and PM'ed.

Week of July 4, 2011

Currently running under standard operating conditions

July 4, 2011 down for the holiday

Week of June 27, 2011

Currently running under standard operating conditions

Week of June 20, 2011

Currently running under standard operating conditions

Week of June 13, 2011

Currently running under standard operating conditions

Week of June 6, 2011

Currently running under standard operating conditions

Week of May 30, 2011

Currently running under standard operating conditions

May 31, 2011 and June 1, 2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of May 23, 2011

Currently running under standard operating conditions

Week of May 16, 2011

Currently running under standard operating conditions

May 12, 2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of May 9, 2011

Currently running under standard operating conditions

May 6-8, 2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of May 2, 2011

Currently running under standard operating conditions

Week of April 25, 2011

Currently running under standard operating conditions

April 29, 2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of April 18, 2011

Currently running under standard operating conditions

Week of April 11, 2011

Currently running under standard operating conditions

Week of April 4, 2011

Currently running under standard operating conditions

Week of March 28, 2011

Currently running under standard operating conditions

March 31, 2011 down for equipment maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Week of March 21, 2011

Currently running under standard operating conditions

Week of March 14, 2011

Down for equipment maintenance this week. During this time the Scrubber, cyclone and fan will be inspected and PM'ed

Week of March 7, 2011

Currently running under standard operating conditions

Week of February 28, 2011

Currently down for equipment maintenance. During this time the Scrubber, cyclone and fan will be inspected and PM'ed

Week of February 21, 2011

Currently running under standard operating conditions

Weeks of January 3, 2011 throught February 14, 2011

Please note that the February 16, 2011 Community Meeting, to review plant environmental performance will be held at 7:00 pm at the Dobisky Center on 100 Riverside Avenue

Currently running under standard operating conditions

February 1, 2011 down for Maintenance

During this time the Scrubber, cyclone and fan were inspected and PM'ed.


Please note that the January 19, 2011 Community Meeting, to review plant environmental performance will include a presentation on the stack test results. It will be held at 7:00 pm at the Dobisky Center on 100 Riverside Avenue

_____________________________________________________________________
Hoosier Magnetics, Inc.
Ogdensburg Plant
110 Denny Street, Ogdensburg
Phone: 393-1813

Residential Public Meeting Notice

Meeting Date: 3rd Wednesday of each month.
2011 schedule is below.

Meeting Time: 7:00 p.m.

Location: Dobisky Center
100 Riverside Avenue
Ogdensburg, NY 13669
Conference Room

Agenda: Review plant environmental performance

Presentation by Plant Manager
Question and Answer Session

Neighbor Requested Agenda Item: TBD

Please contact the Plant Manager prior to the meeting at 393-1813 x 111
To request an agenda item be added

All neighborhood residents are welcome.
“Hoosier Huddle” Public Meeting Schedule 2011:
January 19, 2011 7:00 p.m.
February 16, 2011 7:00 p.m.
March 16, 2011 7:00 p.m.
April 20, 2011 7:00 p.m.
May 18, 2011 7:00 p.m.
June 15, 2011 7:00 p.m.
July 20, 2011 7:00 p.m.
August 17, 2011 7:00 p.m.
September 21, 2011 7:00 p.m.
October 19, 2011 7:00 p.m.
November 16, 2011 7:00 p.m.
December 21, 2011 7:00 p.m.

A meeting schedule for 2012 will be provided at the December 2011 meeting.
_____________________________________________________________________

Week of December 27, 2010 down for Maintenance

During this time the Scrubber, cyclone and fan were inspected and PM'ed.

Weeks of December 6, 2010 through December 20, 2010

Currently running under standard operating conditions


Please note that the December 15, 2010 Community Meeting, to review plant environmental performance, will be held at 7:00 pm at the Dobisky Center on 100 Riverside Avenue


Down for Thanksgiving Holiday, November 25 and 26, 2010

During this time the Scrubber, cyclone and fan were inspected and PM'ed.

Weeks of September 27, 2010 through November 22, 2010

Please note that the November 17, 2010 Community Meeting, to review plant environmental performance, will be held at 7:00 pm at the Dobisky Center on 100 Riverside Avenue

Currently running under standard operating conditions

September 20, 2010 week down for maintenance

During this time the environmental controls were replaced.

Weeks of August 9, 2010 through September 13, 2010

September 9, 2010 down for maintenance

During this time the Scrubber, cyclone and fan were inspected and PM'ed.

Currently running under standard operating conditions

August 25, 2010 Kiln was down for maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed.

Week of August 2, 2010 down for maintenance

During this time the Scrubber, cyclone and fan were inspected and PM'ed.

Weeks of June 2, 2010 through July 26, 2010

Currently running under standard operating conditions

July 24 Kiln was down for maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed.

June 30 Kiln was down for maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed.

____________________________________________________________________
Hoosier Magnetics, Inc.
Ogdensburg Plant
110 Denny Street, Ogdensburg
Phone: 393-1813


Residential Public Meeting Notice


Meeting Date: 3rd Wednesday of each month. 2010 schedule is below.

Meeting Time: 7:00 p.m.

Location: Hoosier Magnetics Inc.
110 Lower Denny Street
Ogdensburg, NY 13669
Conference Room

Agenda: Review plant environmental performance

Presentation by Plant Manager
Question and Answer Session


All neighborhood residents are welcome.

“Hoosier Huddle” Public Meeting Schedule 2010:
January 20, 2010 7:00 p.m.
February 17, 2010 7:00 p.m.
March 17, 2010 7:00 p.m.
April 21, 2010 7:00 p.m.
May 19, 2010 7:00 p.m.
June 16, 2010 7:00 p.m.
July 21, 2010 7:00 p.m.
August 18, 2010 7:00 p.m.
September 15, 2010 7:00 p.m.
October 20, 2010 7:00 p.m.
November 17, 2010 7:00 p.m.
December 15, 2010 7:00 p.m.


A meeting schedule for 2011 will be provided at the December 2010 meeting.
____________________________________________________________________

June 9 Kiln was down for maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed.

May 31 and June 1 Kiln was down for maintenance. During this time the Scrubber, cyclone and fan were inspected and PM'ed

Weeks of April 5, 2010 through May 28, 2010

Currently running under standard operating conditions

May 13, Kiln was down for maintenance. During this time the Scrubber, cyclone and fan were inspected/PM'ed

Currently running under standard operating conditions

May 3, Kiln was down for maintenance. During this time the Scrubber, cyclone and fan were inspected/PM'ed

April 19, Kiln down for maintenance. During this time the Scrubber, cyclone and fan were inspected/PM'ed

Weeks of March 22, 2010 and March 29, 2010

Down for Maintenance

During this time the Scrubber, cyclone and Fan were inspected/PM'ed

Weeks of March 1, 2010 through March 15, 2010

Currently running under standard operating conditions

Week of February 22, 2010 Down for Maintenance on the Kiln.

During this time the Scrubber, cyclone and Fan were inspected/PM'ed

Weeks of January 25, 2010 through February 15,2010

Currently running under standard operating conditions

February 12, Kiln down for maintenance. During this time the Scrubber was inspected/PM'ed

January 22 & 27, Kiln down for maintenance. During this time the Scrubber, cyclone and Fan were inspected/PM'ed

Currently running under standard operating conditions


Weeks of January 2, 2010 through January 18, 2010

January 20, Kiln down for a few hours, During this time the Scrubber and Fan was inspected/PM'ed

Currently running under standard operating conditions


December 24, 2009 through January 1, 2010

Down for Maintenance

During this time the complete Environmental control system will be inspected/PM'ed - Cyclone, Scrubber and Fan.


Weeks of November 30, 2009 through December 21, 2009

Currently running under standard operating conditions

December 1, Kiln down for a few hours, During this time the Scrubber and Fan was inspected/PM'ed


December 5, Kiln down for a few hours. During this time the Scrubber and Fan were inspected/PM'ed


November 23, 2009

Currently down for maintenace and Thanksgiving

During this time the complete Environmental control system was inspected/PM'ed - Cyclone, Scrubber and Fan.


Weeks of October 26, 2009 through November 16, 2009

Currently running under standard operating conditions

November 10, 2009 inspected/PM's the Fan

November 4, 2009 inspected/PM's the scrubber

October 26, 2009 inspection of Environmental conrol system post pipe installation


October 19 & 20, 2009 Line 2 Environmental control systems had a pipe replaced. During this time the complete Environmental control system was inspected/PM'ed - Cyclone, Scrubber and Fan.


Weeks of October 5, 2009 throught October 19, 2009

Currently running under standard operating conditions

October 15, 2009 Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan.

There will be a few days of maintenance during the week of October 19th.


Weeks of September 21, 2009 through September 28, 2009

Currently running under standard operating conditions

Down for a few hours on October 2nd - power outage

Down for a few hours on September 20th - power outage


September 17 & 18 Down for Maintenance

Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan


Week of September 7, 2009 through September 14, 2009

Currently running under standard operating conditions
There will be a few days of maintenance during the week of September 14th.


Week of August 24, 2009 through August 31, 2009

Currently running under standard operating conditions


Week of August 17, 2009

Currently running under standard operating conditions

Down for 3 days for maintenance

Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan.


Weeks of May 26, 2009 through August 10, 2009

Currently running under standard operating conditions.


July 31, 2009 Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan.


July 24, 2009 Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan.


July 10, 2009 Line 2 Environmental control systems inspected/PM'ed - Scrubber and Fan.


July 2, 2009 Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan.


June 19, 2009 Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan.


June 4 & 5, 2009 Line 2 Environmental control systems inspected/PM'ed - Cyclone, Scrubber and Fan.


Week of May 18, 2009


Currently down for maintenace

May 15, 2009 Line 2 Environmental control systems inspected - Cyclone, Scrubber and Fan.


_____________________________________________________________________

Hoosier Magnetics, Inc.
Ogdensburg Plant
110 Denny Street, Ogdensburg
Phone: 393-1813

Residential Public Meeting Notice


Meeting Date: 2nd Tuesday of each month. 2009 schedule is below.

Meeting Time: 7:00 p.m.

Location: Hoosier Magnetics Inc.
110 Lower Denny Street
Ogdensburg, NY 13669
Conference Room

Agenda: Presentation by Plant Manager
Question and Answer Session


All neighborhood residents are welcome.

“Hoosier Huddle” Public Meeting Schedule 2009:

May 12, 2009 7:00 p.m.
June 9, 2009 7:00 p.m.
July 14, 2009 7:00 p.m.
August 11, 2009 7:00 p.m.
September 8, 2009 7:00 p.m.
October 13, 2009 7:00 p.m.
November 10, 2009 7:00 p.m.
December 8, 2009 7:00 p.m.

A meeting schedule for 2010 will be provided at the December 2009 meeting.
_____________________________________________________________________

Weeks of April 20, 2009 through May 11, 2009


Currently running under standard operating conditions.

May 1, 2009 Line 2 Environmental control systems inspected - Cyclone, Scrubber and Fan.


Weeks of March 16, 2009 thru week of April 13, 2009

Currently down for maintenance.


Week of March 9, 2009

Currently running under standard operating conditions.

March 12, 2009 Line 2 scrubber inspected and pm'ed.


Week of March 2, 2009

Currently running under standard operating conditions.

March 5, 2009 Line 2 cyclone inspected and scrubber inspected and pm'ed.

 


 





 

 